Walker Sime - Celebrating 10 Years of Success 2000 - 2010
 
HOME
WHAT WE DO
WHERE WE WORK
OUR PROJECTS
OUR PEOPLE
CAREERS
LINKS
CONTACT US
OUR NEWS


PROJECT PROFILES
Mixed Use Development, Townside Fields, Bury
 
This project required a multi-utility installation that included two separate distribution sub-stations.  The site itself was very restricted, and the off-site mains route was particularly challenging. The installation of BT infrastructure was also included in the scheme.
 
The Client had accepted a quotation for the works twelve months previously, but the project appeared to have stalled. Problems included:
Escalating costs
Inability to get design approval for the electrical works
A quotation that did not meet the technical requirements of the scheme
Inability to secure a temporary supply of sufficient size
Programme Conflicts
 
Using our experience of delivering large multi-utility schemes, Walker Sime were able to achieve the following:
A re-quote that was actually lower than the original, and that included an agreement to waive any inflationary uplift for a further twelve months.
Greater cost certainty for the Client. Additional works that would have been required to meet the Client's particular programme and energisation requirements were identified in advance and incorporated into the re-quote.
A fully optimized design that met both the technical and logistical requirements of the scheme and the approval of the asset owner.
A scheme that allowed for the large temporary supply required. By carefully managing the works, this was achieved at an extremely low additional cost to the main scheme.
 
<<< Back
 
Copyright © Walker Sime 2009               "Delivering quality through professionalism, enthusiasm and commitment"